What this controls
The handoff transfers the basis of the price, not just the total. Operations should be able to reproduce the submitted amount, see where the risk sits, and act without guessing what estimating meant.
Free working tool · No signup
A won bid is not a field plan. Check the nine controls below, then run the review. The result tells you whether the handoff is ready, conditional, or still on hold.
Private by design. This page has no project fields. Checkbox state stays in this tab, and measurement records only that the checklist or review was used—never which items you checked.
The handoff transfers the basis of the price, not just the total. Operations should be able to reproduce the submitted amount, see where the risk sits, and act without guessing what estimating meant.
This is an internal workflow check. It does not replace the contract, project specifications, safety planning, legal review, accounting controls, or requirements specific to the owner and jurisdiction.
Give the package to the person who owns delivery. If that person cannot name the scope boundary, current open items, and next three actions without calling the estimator back, the handoff is not done.
Plain answers
After the award basis is known and before purchasing, detailing, scheduling, or field commitments outrun the estimate. If an early release is required, label exactly what is released and what remains conditional.
The estimator and the person accepting operational ownership are the minimum. Add purchasing, accounting, detailing, field leadership, or safety when the package gives them a real next action.
The controlled bid basis. It ties the final number to the plans, addenda, proposal, quotes, inclusions, exclusions, and assumptions that produced it.